Dept. of Trans. PROGRESS Serial No. Contract No. 09-355-15-58 11-296804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 74% 74% 11-SD-125-9.6/T20.8 Federal Project: NONE Progress payment No. 02 Payment period ending: 12-20-09 VALLEY SLURRY SEAL COMPANY P O BOX 981330 WEST SACRAMENTO CA 95798 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 545,803.68 51,514.34 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 545,803.68 51,514.34 5. Mobilization 85,000.00 0.00 6. Total Work Completed 630,803.68 7. Deductions -95,000.00 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 535,803.68 41,514.34 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 41,514.34