Dept. of Trans. PROGRESS Serial No. Contract No. 13-057-14-47 11-2976U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 73% 19% 11-SD-5-R10.0/R10.0 Federal Project: HPLU-6211(115) Progress payment No. 05 Payment period ending: 02-20-13 L B CIVIL CONSTRUCTION INC 11585 SORRENTO VALLEY RD #104 SAN DIEGO CA 92121 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,136,614.15 193,850.10 2.a. Extra Work 33,147.21 32,804.20 b. Adjustment Comp. -184.23 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,169,577.13 226,654.30 5. Mobilization 139,000.00 0.00 6. Total Work Completed 1,308,577.13 7. Deductions -10,000.00 -6,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,298,577.13 220,654.30 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 220,654.30