Dept. of Trans. PROGRESS Serial No. Contract No. 13-081-10-28 11-2976U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 82% 24% 11-SD-5-R10.0/R10.0 Federal Project: HPLU-6211(115) Progress payment No. 06 Payment period ending: 03-20-13 L B CIVIL CONSTRUCTION INC 11585 SORRENTO VALLEY RD #104 SAN DIEGO CA 92121 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,308,692.05 172,077.90 2.a. Extra Work 53,007.34 19,860.13 b. Adjustment Comp. -553.40 -369.17 3. Materials on Hand 4. Earned Subject to Retention 1,361,145.99 191,568.86 5. Mobilization 139,000.00 0.00 6. Total Work Completed 1,500,145.99 7. Deductions -5,000.00 5,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,495,145.99 196,568.86 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 196,568.86