Dept. of Trans. PROGRESS Serial No. Contract No. 13-141-11-46 11-2976U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 96% 34% 11-SD-5-R10.0/R10.0 Federal Project: HPLU-6211(115) Progress payment No. 08 Payment period ending: 05-20-13 L B CIVIL CONSTRUCTION INC 11585 SORRENTO VALLEY RD #104 SAN DIEGO CA 92121 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,630,058.30 1,276.00 2.a. Extra Work 84,514.85 21,095.19 b. Adjustment Comp. -1,233.80 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,713,339.35 22,371.19 5. Mobilization 139,000.00 0.00 6. Total Work Completed 1,852,339.35 7. Deductions -5,000.00 2,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,847,339.35 24,371.19 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 24,371.19