Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 14-106-11-45 11-2976U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 11-SD-5-R10.0/R10.0 Federal Project: HPLU-6211(115) Progress payment No. 18 Payment period ending: 04-11-14 L B CIVIL CONSTRUCTION INC 11585 SORRENTO VALLEY RD #104 SAN DIEGO CA 92121 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,664,773.30 0.00 2.a. Extra Work 91,963.26 0.00 b. Adjustment Comp. -3,857.58 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,752,878.98 0.00 5. Mobilization 139,000.00 0.00 6. Total Work Completed 1,891,878.98 7. Deductions -22,000.00 -21,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,869,878.98 -21,000.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate -21,000.00