Dept. of Trans. PROGRESS Serial No. Contract No. 13-262-07-49 11-298604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 99% 49% 11-SD-8-10.5/12.6 Federal Project: ACIM-081(311) G-081(311) Progress payment No. 07 Payment period ending: 09-20-13 L B CIVIL CONSTRUCTION INC 11585 SORRENTO VALLEY RD #104 SAN DIEGO CA 92121 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,945,319.99 26,289.50 2.a. Extra Work 235,450.84 8,429.50 b. Adjustment Comp. 20,476.70 -5,316.55 3. Materials on Hand 4. Earned Subject to Retention 2,201,247.53 29,402.45 5. Mobilization 182,000.00 0.00 6. Total Work Completed 2,383,247.53 7. Deductions -10,000.00 -4,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,373,247.53 25,402.45 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 25,402.45