Dept. of Trans. PROGRESS Serial No. Contract No. 18-332-09-04 11-299104 PROGRESS PAYMENT VOUCHER %complete: %time: 38% 95% Location: Federal Project: 11-SD-76-22.2/40.0 ACST-P076(31) Progress payment No. 007 Payment period ending: 11-20-18 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 435,262.36 0.00 2. a. Extra Work 16,457.30 9,912.22 b. Adustment Comp. 3. Materials on Hand 107,651.16 107,651.16 4. Earned Subject to Retention 559,370.82 117,563.38 5. Mobilization 94,050.00 0.00 6. Total Work Completed 545,769.66 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 653,420.82 117,563.38 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 117,563.38