Dept. of Trans. PROGRESS Serial No. Contract No. 19-018-12-05 11-299104 PROGRESS PAYMENT VOUCHER %complete: %time: 54% 100% Location: Federal Project: 11-SD-76-22.2/40.0 ACST-P076(31) Progress payment No. 009 Payment period ending: 01-20-19 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 659,796.80 104,830.07 2. a. Extra Work 35,054.59 18,597.29 b. Adustment Comp. 3. Materials on Hand 68,882.39 0.00 4. Earned Subject to Retention 763,733.78 123,427.36 5. Mobilization 99,000.00 4,950.00 6. Total Work Completed 793,851.39 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions -20,436.30 -12,342.74 c. Reduction after 95% Comp. 9. Total pay to Contractor 842,297.48 116,034.62 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 116,034.62