Dept. of Trans. PROGRESS Serial No. Contract No. 19-055-08-20 11-299104 PROGRESS PAYMENT VOUCHER %complete: %time: 59% 100% Location: Federal Project: 11-SD-76-22.2/40.0 ACST-P076(31) Progress payment No. 010 Payment period ending: 02-20-19 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 731,715.91 71,919.11 2. a. Extra Work 43,166.67 8,112.08 b. Adustment Comp. 3. Materials on Hand 68,881.99 -0.40 4. Earned Subject to Retention 843,764.57 80,030.79 5. Mobilization 99,000.00 0.00 6. Total Work Completed 873,882.58 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions -28,439.38 -8,003.08 c. Reduction after 95% Comp. 9. Total pay to Contractor 914,325.19 72,027.71 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 72,027.71