Dept. of Trans. PROGRESS Serial No. Contract No. 19-084-10-10 11-299104 PROGRESS PAYMENT VOUCHER %complete: %time: 69% 100% Location: Federal Project: 11-SD-76-22.2/40.0 ACST-P076(31) Progress payment No. 011 Payment period ending: 03-20-19 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 867,069.33 135,353.42 2. a. Extra Work 43,166.67 0.00 b. Adustment Comp. 3. Materials on Hand 59,971.97 -8,910.02 4. Earned Subject to Retention 970,207.97 126,443.40 5. Mobilization 99,000.00 0.00 6. Total Work Completed 1,009,236.00 7. Deductions -2,000.00 -2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions 0.00 28,439.38 c. Reduction after 95% Comp. 9. Total pay to Contractor 1,067,207.97 152,882.78 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 152,882.78