Dept. of Trans. PROGRESS Serial No. Contract No. 19-112-16-45 11-299104 PROGRESS PAYMENT VOUCHER %complete: %time: 84% 100% Location: Federal Project: 11-SD-76-22.2/40.0 ACST-P076(31) Progress payment No. 012 Payment period ending: 04-20-19 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,069,444.08 202,374.75 2. a. Extra Work 62,213.95 19,047.28 b. Adustment Comp. 3. Materials on Hand 41,769.83 -18,202.14 4. Earned Subject to Retention 1,173,427.86 203,219.89 5. Mobilization 99,000.00 0.00 6. Total Work Completed 1,230,658.03 7. Deductions 0.00 2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,272,427.86 205,219.89 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 205,219.89