Dept. of Trans. PROGRESS Serial No. Contract No. 16-327-16-06 11-299304 PROGRESS PAYMENT VOUCHER %complete: %time: 49% 14% Location: Federal Project: 11-SD-5-R48.7/R59.6 NHPI-005-1(633) Progress payment No. 002 Payment period ending: 11-20-16 SPECTRUM CONSTRUCTION GROUP INC 32 EDELMAN IRVINE CA 92618 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 406,178.42 66,326.59 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 406,178.42 66,326.59 5. Mobilization 186,610.88 0.00 6. Total Work Completed 592,789.30 7. Deductions -70,803.74 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 521,985.56 66,326.59 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 66,326.59