Dept. of Trans. PROGRESS Serial No. Contract No. 16-357-17-17 11-299304 PROGRESS PAYMENT VOUCHER %complete: %time: 64% 21% Location: Federal Project: 11-SD-5-R48.7/R59.6 NHPI-005-1(633) Progress payment No. 003 Payment period ending: 12-20-16 SPECTRUM CONSTRUCTION GROUP INC 32 EDELMAN IRVINE CA 92618 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 597,400.52 191,222.10 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 597,400.52 191,222.10 5. Mobilization 186,610.88 0.00 6. Total Work Completed 784,011.40 7. Deductions -70,803.74 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 713,207.66 191,222.10 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 191,222.10