Dept. of Trans. PROGRESS Serial No. Contract No. 20-296-13-20 11-2E1504 PROGRESS PAYMENT VOUCHER %complete: %time: 99% 100% Location: Federal Project: 11-SD-5-38.1/39.3 NONE Progress payment No. 036 Payment period ending: 10-20-20 FLATIRON-SKANSKA-STACY AND WITBECK A JOINT VENTURE 16470 W BERNARDO DR SAN DIEGO CA 92127 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 72,176,905.50 91,399.50 2. a. Extra Work 3,668,398.97 36,531.16 b. Adustment Comp. -1,396,843.36 50,215.00 3. Materials on Hand 4. Earned Subject to Retention 74,448,461.11 178,145.66 5. Mobilization 9,300,000.00 0.00 6. Total Work Completed 83,748,461.11 7. Deductions -5,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 83,743,461.11 178,145.66 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 178,145.66