Dept. of Trans. PROGRESS Serial No. Contract No. 20-356-12-52 11-2E1504 PROGRESS PAYMENT VOUCHER %complete: %time: 99% 68% Location: Federal Project: 11-SD-5-38.1/39.3 NONE Progress payment No. 038 Payment period ending: 12-20-20 FLATIRON-SKANSKA-STACY AND WITBECK A JOINT VENTURE 16470 W BERNARDO DR SAN DIEGO CA 92127 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 72,344,485.50 75,236.00 2. a. Extra Work 4,237,611.02 567,376.50 b. Adustment Comp. -1,396,843.36 0.00 3. Materials on Hand 4. Earned Subject to Retention 75,185,253.16 642,612.50 5. Mobilization 9,300,000.00 0.00 6. Total Work Completed 84,485,253.16 7. Deductions -5,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 84,480,253.16 642,612.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 642,612.50