Dept. of Trans. PROGRESS Serial No. Contract No. 21-021-17-46 11-2E1504 PROGRESS PAYMENT VOUCHER %complete: %time: 99% 68% Location: Federal Project: 11-SD-5-38.1/39.3 NONE Progress payment No. 039 Payment period ending: 01-20-21 FLATIRON-SKANSKA-STACY AND WITBECK A JOINT VENTURE 16470 W BERNARDO DR SAN DIEGO CA 92127 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 72,428,025.50 83,540.00 2. a. Extra Work 4,902,261.93 664,650.91 b. Adustment Comp. -1,634,819.27 -237,975.91 3. Materials on Hand 4. Earned Subject to Retention 75,695,468.16 510,215.00 5. Mobilization 9,300,000.00 0.00 6. Total Work Completed 84,995,468.16 7. Deductions -10,000.00 -5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 84,985,468.16 505,215.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 505,215.00