Dept. of Trans. PROGRESS Serial No. Contract No. 21-355-13-35 11-2E1504 PROGRESS PAYMENT VOUCHER %complete: %time: 98% 100% Location: Federal Project: 11-SD-5-38.1/39.3 NONE Progress payment No. 050 Payment period ending: 12-20-21 FLATIRON-SKANSKA-STACY AND WITBECK A JOINT VENTURE 16470 W BERNARDO DR #120 SAN DIEGO CA 92127 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 72,911,053.50 2,000.00 2. a. Extra Work 7,953,564.76 2,737,515.13 b. Adustment Comp. -1,951,437.64 27,808.80 3. Materials on Hand 4. Earned Subject to Retention 78,913,180.62 2,767,323.93 5. Mobilization 9,300,000.00 0.00 6. Total Work Completed 88,213,180.62 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 88,213,180.62 2,767,323.93 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,767,323.93