Dept. of Trans. PROGRESS Serial No. Contract No. 22-140-19-17 11-2E1544 PROGRESS PAYMENT VOUCHER %complete: %time: 17% 5% Location: Federal Project: 11-SD-5-34.7/36.3 NONE Progress payment No. 005 Payment period ending: 05-20-22 MARATHON CONSTRUCTION CORPORATION 10108 RIVERFORD RD LAKESIDE CA 92040 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,344,692.85 1,643,370.48 2. a. Extra Work 116,158.20 8,643.12 b. Adustment Comp. 3. Materials on Hand 322,823.60 322,823.60 4. Earned Subject to Retention 6,783,674.65 1,974,837.20 5. Mobilization 4,957,462.50 1,652,487.50 6. Total Work Completed 11,418,313.55 7. Deductions -1,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 11,740,137.15 3,627,324.70 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,627,324.70