Dept. of Trans. PROGRESS Serial No. Contract No. 22-203-11-22 11-2E1544 PROGRESS PAYMENT VOUCHER %complete: %time: 21% 7% Location: Federal Project: 11-SD-5-34.7/36.3 NONE Progress payment No. 007 Payment period ending: 07-20-22 MARATHON CONSTRUCTION CORPORATION 10108 RIVERFORD RD LAKESIDE CA 92040 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,279,182.07 1,726,570.51 2. a. Extra Work 206,817.21 79,300.61 b. Adustment Comp. 3. Materials on Hand 524,755.00 -136,599.10 4. Earned Subject to Retention 10,010,754.28 1,669,272.02 5. Mobilization 4,957,462.50 0.00 6. Total Work Completed 14,443,461.78 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 14,968,216.78 1,669,272.02 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,669,272.02