Dept. of Trans. PROGRESS Serial No. Contract No. 22-231-15-03 11-2E1544 PROGRESS PAYMENT VOUCHER %complete: %time: 25% 8% Location: Federal Project: 11-SD-5-34.7/36.3 NONE Progress payment No. 008 Payment period ending: 08-20-22 MARATHON CONSTRUCTION CORPORATION 10108 RIVERFORD RD LAKESIDE CA 92040 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,973,274.37 2,694,092.30 2. a. Extra Work 432,012.31 225,195.10 b. Adustment Comp. 4,690.67 4,690.67 3. Materials on Hand 0.00 -524,755.00 4. Earned Subject to Retention 12,409,977.35 2,399,223.07 5. Mobilization 4,957,462.50 0.00 6. Total Work Completed 17,367,439.85 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 17,367,439.85 2,399,223.07 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,399,223.07