Dept. of Trans. PROGRESS Serial No. Contract No. 23-022-10-24 11-2E1544 PROGRESS PAYMENT VOUCHER %complete: %time: 39% 13% Location: Federal Project: 11-SD-5-34.7/36.3 NONE Progress payment No. 013 Payment period ending: 01-20-23 MARATHON CONSTRUCTION CORPORATION 10108 RIVERFORD RD LAKESIDE CA 92040 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 19,434,051.36 546,895.92 2. a. Extra Work 1,199,229.55 9,547.20 b. Adustment Comp. 125,685.12 0.00 3. Materials on Hand 454,918.00 -0.20 4. Earned Subject to Retention 21,213,884.03 556,442.92 5. Mobilization 6,279,452.50 0.00 6. Total Work Completed 27,038,418.53 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 27,493,336.53 556,442.92 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 556,442.92