Dept. of Trans. PROGRESS Serial No. Contract No. 24-257-16-19 11-2E1544 PROGRESS PAYMENT VOUCHER %complete: %time: 84% 33% Location: Federal Project: 11-SD-5-34.7/36.3 NONE Progress payment No. 033 Payment period ending: 09-20-24 MARATHON CONSTRUCTION CORPORATION 10108 RIVERFORD RD LAKESIDE CA 92040 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 40,790,100.29 658,114.82 2. a. Extra Work 11,163,324.25 530,763.52 b. Adustment Comp. 253,463.90 -18,443.41 3. Materials on Hand 4. Earned Subject to Retention 52,206,888.44 1,170,434.93 5. Mobilization 6,609,950.00 0.00 6. Total Work Completed 58,816,838.44 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 58,816,838.44 1,170,434.93 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,170,434.93