Dept. of Trans. PROGRESS Serial No. Contract No. 10-264-13-47 11-2M0004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 99% 77% 11-IMP-8-R91.0/R96.8 Federal Project: NONE Progress payment No. 06 Payment period ending: 09-20-10 PAVE TECH INC 735 LAGUNA DRIVE CARLSBAD CA 92008 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 388,406.22 16,226.30 2.a. Extra Work 61,445.87 0.00 b. Adjustment Comp. 9,965.48 0.00 3. Materials on Hand 4. Earned Subject to Retention 459,817.57 16,226.30 5. Mobilization 20,500.00 0.00 6. Total Work Completed 480,317.57 7. Deductions -1,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 479,317.57 16,226.30 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 16,226.30