Dept. of Trans. PROGRESS Serial No. Contract No. 10-236-08-06 11-2M0104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 10% 30% 11-SD-8-L2.4/R67.8 Federal Project: NONE Progress payment No. 01 Payment period ending: 08-20-10 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA SUITE 200 SAN DIEGO CA 92126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 26,719.80 26,719.80 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 26,719.80 26,719.80 5. Mobilization 24,500.00 24,500.00 6. Total Work Completed 51,219.80 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 51,219.80 51,219.80 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 51,219.80