Dept. of Trans. SEMI-FINAL Serial No. Contract No. 11-138-13-35 11-2M0804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 11-SD-8-R31.8/R39.7 Federal Project: ACIM-008-1(304) Progress payment No. 09 Payment period ending: 04-12-11 HAZARD CONSTRUCTION P O BOX 229000 SAN DIEGO CA 921929000 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,293,288.45 0.00 2.a. Extra Work 468,927.83 31,667.75 b. Adjustment Comp. -5,620.79 0.00 3. Materials on Hand 4. Earned Subject to Retention 3,756,595.49 31,667.75 5. Mobilization 250,000.00 0.00 6. Total Work Completed 4,006,595.49 7. Deductions -10,000.00 5,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,996,595.49 36,667.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 36,667.75