Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 11-083-14-52 11-2M1204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 11-SD-56-0.3/2.6 Federal Project: NONE Progress payment No. 08 Payment period ending: 02-23-11 PAVEMENT COATINGS CO 10240 SAN SEVAINE WAY MIRA LOMA CA 91752 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,361,842.28 2,200.00 2.a. Extra Work 235,266.74 57,338.43 b. Adjustment Comp. 74,899.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,672,008.02 59,538.43 5. Mobilization 90,000.00 0.00 6. Total Work Completed 1,762,008.02 7. Deductions -14,000.00 -14,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,748,008.02 45,538.43 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 45,538.43