Dept. of Trans. PROGRESS Serial No. Contract No. 11-236-12-37 11-2M1304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 74% 70% 11-SD-5-R49.7/R62.1 Federal Project: NONE Progress payment No. 02 Payment period ending: 08-20-11 WESTERN STRUCTURES 6005 TYLER STREET RIVERSIDE CA 92503 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 248,647.01 184,018.57 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 248,647.01 184,018.57 5. Mobilization 40,000.00 10,000.00 6. Total Work Completed 288,647.01 7. Deductions -2,915.96 -728.99 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 285,731.05 193,289.58 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 193,289.58