Dept. of Trans. SEMI-FINAL Serial No. Contract No. 12-018-13-10 11-2M1304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 11-SD-5-R49.7/R62.1 Federal Project: NONE Progress payment No. 05 Payment period ending: 10-12-11 WESTERN STRUCTURES 6005 TYLER STREET RIVERSIDE CA 92503 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 328,476.93 0.00 2.a. Extra Work 35,460.64 -189.30 b. Adjustment Comp. 6,740.34 0.00 3. Materials on Hand 4. Earned Subject to Retention 370,677.91 -189.30 5. Mobilization 40,000.00 0.00 6. Total Work Completed 410,677.91 7. Deductions -4,000.00 5,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 406,677.91 4,810.70 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,810.70