Dept. of Trans. PROGRESS Serial No. Contract No. 12-268-10-18 11-2M2004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 85% 100% 11-SD-79-L0.3/10.0 Federal Project: NONE Progress payment No. 03 Payment period ending: 09-20-12 HAZARD CONSTRUCTION COMPANY P O BOX 229000 SAN DIEGO CA 921929000 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,538,652.84 126,580.60 2.a. Extra Work 10,951.03 10,951.03 b. Adjustment Comp. -50,759.72 -50,759.72 3. Materials on Hand 4. Earned Subject to Retention 1,498,844.15 86,771.91 5. Mobilization 185,000.00 0.00 6. Total Work Completed 1,683,844.15 7. Deductions -2,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,681,844.15 86,771.91 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 86,771.91