Dept. of Trans. PROGRESS Serial No. Contract No. 12-298-08-18 11-2M2004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 87% 100% 11-SD-79-L0.3/10.0 Federal Project: NONE Progress payment No. 04 Payment period ending: 10-20-12 HAZARD CONSTRUCTION COMPANY P O BOX 229000 SAN DIEGO CA 921929000 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,566,125.84 27,473.00 2.a. Extra Work 19,226.37 8,275.34 b. Adjustment Comp. -50,759.72 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,534,592.49 35,748.34 5. Mobilization 185,000.00 0.00 6. Total Work Completed 1,719,592.49 7. Deductions -3,000.00 -1,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,716,592.49 34,748.34 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 34,748.34