Dept. of Trans. PROGRESS Serial No. Contract No. 12-332-10-54 11-2M2004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 93% 100% 11-SD-79-L0.3/10.0 Federal Project: NONE Progress payment No. 05 Payment period ending: 11-20-12 HAZARD CONSTRUCTION COMPANY P O BOX 229000 SAN DIEGO CA 921929000 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,671,054.84 104,929.00 2.a. Extra Work 129,782.42 110,556.05 b. Adjustment Comp. -79,980.28 -29,220.56 3. Materials on Hand 4. Earned Subject to Retention 1,720,856.98 186,264.49 5. Mobilization 185,000.00 0.00 6. Total Work Completed 1,905,856.98 7. Deductions -3,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,902,856.98 186,264.49 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 186,264.49