Dept. of Trans. PROGRESS Serial No. Contract No. 13-024-11-43 11-2M2504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 95% 98% 11-IMP-8-R96.8/R96.8 Federal Project: NONE Progress payment No. 04 Payment period ending: 01-20-13 DIAMOND LANE CONTRACTORS P O BOX 630 SOLANA BEACH CA 92075 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 287,511.50 42,205.00 2.a. Extra Work 36,710.42 36,710.42 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 324,221.92 78,915.42 5. Mobilization 25,000.00 0.00 6. Total Work Completed 349,221.92 7. Deductions -10,000.00 -9,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 339,221.92 69,915.42 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 69,915.42