Dept. of Trans. PROGRESS Serial No. Contract No. 12-236-10-21 11-2M3204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 11% 57% 11-SD-5-R11.7/R18.3 Federal Project: NONE Progress payment No. 01 Payment period ending: 08-20-12 PETERSON-CHASE GENERAL ENGINEERING CONSTRUCTION INC 1792 KAISER AVENUE IRVINE CA 92614 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 70,656.67 70,656.67 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 70,656.67 70,656.67 5. Mobilization 44,700.00 44,700.00 6. Total Work Completed 115,356.67 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 115,356.67 115,356.67 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 115,356.67