Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 13-325-12-05 11-2M4104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 11-SD-94-30.0/39.0 Federal Project: NONE Progress payment No. 03 Payment period ending: 11-08-13 HAZARD CONSTRUCTION COMPANY P O BOX 229000 SAN DIEGO CA 921929000 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 875,387.40 184,873.30 2.a. Extra Work 14,624.28 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 890,011.68 184,873.30 5. Mobilization 57,500.00 0.00 6. Total Work Completed 947,511.68 7. Deductions -30,000.00 -30,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 917,511.68 154,873.30 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 154,873.30