Dept. of Trans. PROGRESS Serial No. Contract No. 14-237-10-00 11-2M4904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 84% 52% 11-SD-79-35.1/53.0 Federal Project: NONE Progress payment No. 02 Payment period ending: 08-20-14 CALMEX ENGINEERING INC 2764 S VISTA AVE BLOOMINGTON CA 92316 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,934,995.16 1,843,016.22 2.a. Extra Work 49,994.52 49,994.52 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,984,989.68 1,893,010.74 5. Mobilization 43,389.59 21,694.80 6. Total Work Completed 2,028,379.27 7. Deductions -4,000.00 -4,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,024,379.27 1,910,705.54 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,910,705.54