Dept. of Trans. SEMI-FINAL Serial No. Contract No. 13-274-14-44 11-2M5504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 11-SD-15-31.5/43.0 Federal Project: NONE Progress payment No. 11 Payment period ending: 08-16-13 ALL AMERICAN ASPHALT P O BOX 2229 CORONA CA 928782229 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,570,687.52 0.00 2.a. Extra Work 70,493.69 20,877.43 b. Adjustment Comp. -43,638.99 0.00 3. Materials on Hand 4. Earned Subject to Retention 4,597,542.22 20,877.43 5. Mobilization 141,000.00 0.00 6. Total Work Completed 4,738,542.22 7. Deductions -15,000.00 10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 4,723,542.22 30,877.43 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 30,877.43