Dept. of Trans. PROGRESS Serial No. Contract No. 15-083-06-31 11-2M6304 PROGRESS PAYMENT VOUCHER %complete: %time: 92% 98% Location: Federal Project: 11-SD-76-24.1/34.9 NONE Progress payment No. 007 Payment period ending: 03-20-15 HAZARD CONSTRUCTION COMPANY P O BOX 229000 SAN DIEGO CA 921929000 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,292,148.73 153,806.88 2. a. Extra Work 55,287.55 2,192.80 b. Adustment Comp. -264,188.83 0.00 3. Materials on Hand 4. Earned Subject to Retention 3,083,247.45 155,999.68 5. Mobilization 409,000.00 0.00 6. Total Work Completed 3,492,247.45 7. Deductions -64,338.66 -1,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,427,908.79 154,999.68 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 154,999.68