Dept. of Trans. PROGRESS Serial No. Contract No. 15-111-14-25 11-2M6304 PROGRESS PAYMENT VOUCHER %complete: %time: 96% 98% Location: Federal Project: 11-SD-76-24.1/34.9 NONE Progress payment No. 008 Payment period ending: 04-20-15 HAZARD CONSTRUCTION COMPANY P O BOX 229000 SAN DIEGO CA 921929000 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,407,910.43 115,761.70 2. a. Extra Work 97,508.86 42,221.31 b. Adustment Comp. -264,188.83 0.00 3. Materials on Hand 4. Earned Subject to Retention 3,241,230.46 157,983.01 5. Mobilization 409,000.00 0.00 6. Total Work Completed 3,650,230.46 7. Deductions -66,338.66 -2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,583,891.80 155,983.01 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 155,983.01