Dept. of Trans. FINAL Serial No. Contract No. 16-364-13-54 11-2M6504 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 11-IMP-86-43.1/67.8 STP-P086(74) Progress payment No. 009 Payment period ending: 10-03-16 AMERICAN PAVEMENT SYSTEMS INC 1012 11TH ST #1000 MODESTO CA 95354 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,991,372.15 0.00 2. a. Extra Work 189,797.60 0.00 b. Adustment Comp. 47,496.24 0.00 3. Materials on Hand 4. Earned Subject to Retention 5,228,665.99 0.00 5. Mobilization 278,500.00 0.00 6. Total Work Completed 5,507,165.99 7. Deductions -35,172.39 35,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 5,471,993.60 35,000.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 35,000.00