Dept. of Trans. SEMI-FINAL Serial No. Contract No. 14-328-09-47 11-2M6604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 11-IMP-98-32.3/39.6 Federal Project: STP-P098(25) Progress payment No. 04 Payment period ending: 10-16-14 HAZARD CONSTRUCTION COMPANY P O BOX 229000 SAN DIEGO CA 921929000 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,970,880.90 7,500.00 2.a. Extra Work 114,731.96 67,975.16 b. Adjustment Comp. 30,668.86 -18,654.50 3. Materials on Hand 4. Earned Subject to Retention 2,116,281.72 56,820.66 5. Mobilization 200,000.00 0.00 6. Total Work Completed 2,316,281.72 7. Deductions -25,000.00 5,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,291,281.72 61,820.66 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 61,820.66