Dept. of Trans. PROGRESS Serial No. Contract No. 15-295-12-47 11-2M7704 PROGRESS PAYMENT VOUCHER %complete: %time: 35% 75% Location: Federal Project: 11-IMP-115-R8.5/21.2 NONE Progress payment No. 003 Payment period ending: 10-20-15 MANHOLE ADJSUTING INC 9500 BEVERLY RD PICO RIVERA CA 90660 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 827,235.96 54,415.85 2. a. Extra Work 390.87 390.87 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 827,626.83 54,806.72 5. Mobilization 61,750.00 0.00 6. Total Work Completed 889,376.83 7. Deductions -12,000.00 -2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions -5,480.67 -5,480.67 c. Reduction after 95% Comp. 9. Total pay to Contractor 871,896.16 47,326.05 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 47,326.05