Dept. of Trans. PROGRESS Serial No. Contract No. 16-300-10-17 11-2M8604 PROGRESS PAYMENT VOUCHER %complete: %time: 28% 43% Location: Federal Project: 11-IMP-78-R50.0/80.7 STP-P078(115) Progress payment No. 002 Payment period ending: 10-20-16 AMERICAN PAVEMENT SYSTEMS INC 1012 11TH ST #1000 MODESTO CA 95354 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 454,675.66 358,610.66 2. a. Extra Work 288,949.95 288,949.95 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 743,625.61 647,560.61 5. Mobilization 237,500.00 237,500.00 6. Total Work Completed 981,125.61 7. Deductions -10,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 971,125.61 875,060.61 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 875,060.61