Dept. of Trans. PROGRESS Serial No. Contract No. 17-297-16-26 11-2M9404 PROGRESS PAYMENT VOUCHER %complete: %time: 77% 53% Location: Federal Project: 11-IMP-115-R3.2/R8.5 ACST-P115(12) Progress payment No. 003 Payment period ending: 10-20-17 MANHOLE ADJUSTING INC 9500 BEVERLY RD PICO RIVERA CA 90660 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,404,703.19 630,749.18 2. a. Extra Work 43,403.40 43,403.40 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,448,106.59 674,152.58 5. Mobilization 429,350.00 21,467.50 6. Total Work Completed 1,877,456.59 7. Deductions -204,097.20 -9,954.86 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,673,359.39 685,665.22 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 685,665.22