Dept. of Trans. PROGRESS Serial No. Contract No. 21-322-08-52 11-2N0084 PROGRESS PAYMENT VOUCHER %complete: %time: 16% 24% Location: Federal Project: 11-IMP-7-0.4/6.3 NONE Progress payment No. 003 Payment period ending: 11-20-21 FEC FUTURE CONTRACTORS AND ENGINEERS INC 184 TECHNOLOGY DRIVE #205 IRVINE CA 92618 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 276,384.35 71,238.27 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 27,913.00 720.00 4. Earned Subject to Retention 304,297.35 71,958.27 5. Mobilization 238,500.00 79,500.00 6. Total Work Completed 514,884.35 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 542,797.35 151,458.27 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 151,458.27