Dept. of Trans. PROGRESS Serial No. Contract No. 19-112-13-54 11-2N0104 PROGRESS PAYMENT VOUCHER %complete: %time: 77% 81% Location: Federal Project: 11-IMP-111-R1.2/R8.3 NONE Progress payment No. 010 Payment period ending: 04-20-19 SECURITY PAVING COMPANY INC 13170 TELFAIR AVE SYLMAR CA 91342 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,430,216.14 1,250,410.89 2. a. Extra Work 82,454.91 2,465.63 b. Adustment Comp. -2,918.11 -6,168.91 3. Materials on Hand 4. Earned Subject to Retention 13,509,752.94 1,246,707.61 5. Mobilization 743,252.80 0.00 6. Total Work Completed 14,253,005.74 7. Deductions -76,908.13 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 14,176,097.61 1,246,707.61 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,246,707.61