Dept. of Trans. SEMI-FINAL Serial No. Contract No. 20-080-13-47 11-2N0104 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 11-IMP-111-R1.2/R8.3 NONE Progress payment No. 017 Payment period ending: 09-10-19 SECURITY PAVING COMPANY INC 3075 TOWNSGATE RD #200 WESTLAKE VILLAGE CA 91361 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,284,480.43 8,300.40 2. a. Extra Work 1,297,311.06 345,864.59 b. Adustment Comp. -9,113.78 0.00 3. Materials on Hand 4. Earned Subject to Retention 16,572,677.71 354,164.99 5. Mobilization 743,252.80 0.00 6. Total Work Completed 17,315,930.51 7. Deductions -602,296.14 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 16,713,634.37 354,164.99 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 354,164.99