Dept. of Trans. PROGRESS Serial No. Contract No. 19-262-13-38 11-2N0144 PROGRESS PAYMENT VOUCHER %complete: %time: 43% 71% Location: Federal Project: 11-SD-15-10.9/19.5 NONE Progress payment No. 007 Payment period ending: 09-20-19 HAZARD CONSTRUCTION COMPANY PO BOX 229000 SAN DIEGO CA 921929000 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,896,753.54 876,200.80 2. a. Extra Work 60,027.08 0.00 b. Adustment Comp. 3. Materials on Hand 34,100.23 -12,137.46 4. Earned Subject to Retention 1,990,880.85 864,063.34 5. Mobilization 513,000.00 0.00 6. Total Work Completed 2,469,780.62 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,503,880.85 864,063.34 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 864,063.34