Dept. of Trans. PROGRESS Serial No. Contract No. 22-144-12-05 11-2N0724 PROGRESS PAYMENT VOUCHER %complete: %time: 10% 68% Location: Federal Project: 11-IMP-111-R0.1/R1.2 NONE Progress payment No. 001 Payment period ending: 05-20-22 PAL GENERAL ENGINEERING INC 2346 PASEO DE LAS AMERICAS #1 SAN DIEGO CA 92154 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 145,805.50 145,805.50 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 145,805.50 145,805.50 5. Mobilization 55,000.00 55,000.00 6. Total Work Completed 200,805.50 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 200,805.50 200,805.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 200,805.50