Dept. of Trans. PROGRESS Serial No. Contract No. 22-356-10-36 11-2N1154 PROGRESS PAYMENT VOUCHER %complete: %time: 77% 58% Location: Federal Project: 11-IMP-115-R3.2/R8.8 NONE Progress payment No. 003 Payment period ending: 12-20-22 AMERICAN PAVEMENT SYSTEMS INC 1012 11TH ST #1000 MODESTO CA 95354 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,155,943.28 530,080.46 2. a. Extra Work 8,632.46 5,178.01 b. Adustment Comp. -62,433.57 -62,433.57 3. Materials on Hand 4. Earned Subject to Retention 2,102,142.17 472,824.90 5. Mobilization 600,000.00 30,000.00 6. Total Work Completed 2,702,142.17 7. Deductions -253,993.00 -12,699.65 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,448,149.17 490,125.25 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 490,125.25