Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 24-038-09-51 11-2N1194 PROGRESS PAYMENT VOUCHER %complete: %time: 86% 100% Location: Federal Project: 11-SD-94-14.9/29.2 NONE Progress payment No. 006 Payment period ending: 01-20-24 VSS INTERNATIONAL INC 3785 CHANNEL DRIVE WEST SACRAMENTO CA 95691 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,704,828.83 -543,020.08 2. a. Extra Work 994,992.00 994,992.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 3,699,820.83 451,971.92 5. Mobilization 161,330.73 0.00 6. Total Work Completed 3,861,151.56 7. Deductions -259,600.00 104,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions 0.00 308,066.85 c. Reduction after 95% Comp. 9. Total pay to Contractor 3,601,551.56 864,038.77 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 864,038.77